Site preparation & protection
Step 14Checking the site
Before work starts, we check the site and take photos of its condition, meters, keys and areas to protect.
Step 15Society rules and site setup
We check society rules, working hours, lift use, water, electricity and waste removal. You and our team agree on who handles what.
Step 16Protecting floors and doors
We cover the floors, doors and lift areas that must stay safe. The cover is changed as work goes on.
Step 17Marking the site
We mark furniture, ceiling levels, lights and switches on the walls and floor, as per the approved drawings. Problems are fixed on paper before work starts.
Civil, ceiling, electrical & wall preparation
Step 18Civil work (if needed)
Breaking, masonry or levelling work is done only where needed. If waterproofing is included, it is done and tested before surfaces are covered.
Step 19Plumbing and AC pipes
Plumbing, drain points, AC pipes and ducts are planned before walls or ceilings are closed.
Step 20False ceiling frame
The ceiling team marks levels and builds the frame — keeping space for fans, curtains, AC vents and lights.
Step 21Electrical wiring
The electrician lays the wiring along with the ceiling work. All wiring is tested before the ceiling and walls are closed.
Step 22Closing the false ceiling
After wiring and checks, ceiling boards are fixed and the joints are finished.
Step 23Wall repair, putty and primer
Walls are repaired, then putty and primer are applied. The last paint coat is kept for the end, so carpentry does not damage it.
Furniture, materials & fittings
Step 24Final furniture marking
Before furniture is made, we measure the walls and openings again and match them with the drawings.
Step 25Making the furniture
Wardrobes, kitchen, TV unit, beds and other furniture are made in our workshop or on site, as per the approved sizes and materials.
Step 26Buying and checking materials
We order materials as the work needs them and check them on delivery. Any change in material needs your approval.
Step 27Flooring, stone and tiles (if included)
Tile, stone and flooring work is done at the right time, and nearby finished areas are covered.
Step 28Furniture and kitchen installation
The team fits cabinets, shutters, drawers, countertops and furniture, and checks that everything opens and aligns properly.
Step 29Wall panels, doors and glass
Decorative panels, mirrors, glass, doors and wallpaper are fitted by skilled workers.
Step 30Final painting and touch-ups
After heavy work is done, the final paint coats and touch-ups are applied carefully around the furniture.
Step 31Lights, switches, hardware and appliances
Lights, switches, handles, sanitary fittings and kitchen appliances are fitted and checked. Electrical safety checks are done by trained people.
Supervision & updates. ML Sharma personally supervises site execution, with daily visits on active Udaipur projects and an agreed plan for outstation sites. Progress is shared in your project’s dedicated WhatsApp group. Any extra work is discussed and priced first — nothing extra is charged without your approval.